Faultory

Case file 69 · Engineering & technology

The wind that came from the corner

Citicorp Center, New York, 1978: how did the engineer find that the tower could fall in a storm, and what made the risk worse?

Subject
Citicorp Center wind-bracing crisis (1978)
Reading
14 min
Evidence
5 exhibits
Reasoning
4 steps
Level
Advanced
Illustrative signature. An illustrative strip-chart sketch of tower sway as a storm builds and passes, growing with wind and easing after the peak (a sketch, not measured data). Drawn to explain the case, not plotted from source data.

01 · The briefing

Begin with the question.

Citicorp Center was a 59-story tower on Lexington Avenue in Midtown Manhattan, designed by the architect Hugh Stubbins with William LeMessurier as structural engineer, and completed in 1977. It stood on four massive columns placed at the middle of each side rather than at the corners, so its corners were cantilevered out. Its wind bracing used steel chevrons, and the joints connecting them had been specified as welds. In 1974 the steel contractor proposed bolted joints instead, and the engineer's New York office accepted the change without the engineer himself learning of it. In June 1978 a student's question about the columns led the structural engineer, William LeMessurier, to recalculate the braces for diagonal winds, which strike the corners. Commentators have framed the episode in different ways: as a design error, as a construction change, or as a question of how a risk should be disclosed. This investigation separates three things: the calculations and the joint change, the storm odds and the repairs, and the account of how the problem reached the engineer, which varies between sources. The question is how the risk arose and why the response was delayed in public.

The timeline

  1. The New York office of the structural engineer accepts Bethlehem Steel's proposal to use bolted instead of welded wind-brace joints.

  2. A student's call prompts the engineer to recalculate the braces for diagonal (quartering) winds; strain rises by about 40 percent in four of the eight chevrons in each tier.

  3. The engineer meets Alan Davenport in London, Ontario, to test the new calculations against the wind-tunnel data.

  4. Citicorp publicly announces a review of the wind bracing, stating that there is no danger.

  5. Hurricane Ella approaches New York, and an emergency-planning group convenes to plan for a possible evacuation.

  6. Welding of steel plates over the bolted joints is completed, several weeks before the city's newspapers resume publication.

  7. The New Yorker publishes Joseph Morgenstern's article, which becomes the main public account of the 1978 episode.

A researched reconstruction for learning. These reasoning steps simplify a complex record; no score can capture the full history.

02 · The evidence

What does the record show?

Read each exhibit before settling on an explanation. The source links below every exhibit lead to the record behind it.

Exhibit 01

A joint change that the engineer did not know about

Joseph Morgenstern's 1995 New Yorker article says that the wind braces were first specified with welded joints. In 1974 Bethlehem Steel argued that welds were stronger than needed and proposed bolts, and on 1 August 1974 the New York office of the engineer, a venture with an older Manhattan firm, accepted the proposal. The engineer learned of the change only in May 1978, during a meeting at his Cambridge office, when a call to his New York office confirmed that the welds had never been made. The article establishes the change and when the engineer found out. Much of the account rests on the engineer's own recollection.

Source record s1newyorker.com

Exhibit 02

Diagonal winds and the weakest joint

The New Yorker article says that the braces had been checked only against winds blowing straight at each face, which was the calculation the New York building code required. After a student's call about the columns, the engineer recalculated for winds at 45 degrees. In four of the eight chevrons in each tier, the strain rose by about 40 percent. Wind-tunnel results from Alan Davenport's laboratory at the University of Western Ontario, with and without the tuned mass damper, then helped identify the weakest joint, at the building's thirtieth floor. The figures are the engineer's own, drawn from one narrative account.

Source record s1newyorker.com

Exhibit 03

Storm odds before and after the repair

The New Yorker article gives the storm odds in the engineer's terms. Without the tuned mass damper, the calculated chance that a storm would tear the weakest joint apart was one in sixteen in any year. With the damper running, the figure was one in fifty-five. The damper needed electric power, which might fail in a major storm. After the repairs, the article says, the building could withstand a seven-hundred-year storm even without the damper; the landmarks report attributes that claim to the engineer. These are per-year estimates drawn from New York weather records, and the article describes the models only in summary.

Source record s1newyorker.com

Exhibit 04

The repairs and how the record names the student

The 2016 designation report of New York City's Landmarks Preservation Commission says the repairs involved welding two-inch steel plates over more than two hundred bolted joints. The work took about two months, ending in October 1978. The report says that Diane Hartley, a graduate student at Princeton University, brought the quartering-wind question to the New York office, and that Citicorp hired Leslie Robertson to supervise the repairs. Because the city's newspapers were on strike, the story stayed largely unknown until 1995. The New Yorker gives a different account of the call, describing a student from New Jersey who phoned the Cambridge office, and it does not name him.

Source record s2s-media.nyc.gov

Exhibit 05

A modern analysis of a similar building

A 2019 paper in the Journal of Structural Engineering, by four authors at the National Institute of Standards and Technology, models a tall square building with mid-side base columns that it describes as similar to Citicorp Center. Using public wind-tunnel data and a database-assisted design method, it finds corner winds less demanding than face winds: overturning moments are about 20 and 50 percent lower in the two directions, and the demand measures for the members it checks, including chevron braces, are lower too. The authors suggest the Citicorp design and retrofit history may warrant re-examination. The paper does not reconstruct the 1978 calculations.

Source record s3pmc.ncbi.nlm.nih.gov

03 · Your reasoning

Follow the strongest explanation.

Choose an interpretation, then compare it with the evidence. You can revise your choice. The goal is understanding, not a perfect score.

Reasoning step 01 of 04

Which change explains why the joints were weaker than the design assumed?

Evidence-based explanation

The New Yorker article reports that the braces were specified for welded joints, that Bethlehem Steel proposed bolts, and that the New York office accepted the change; the landmarks report confirms that the repaired joints were bolted. The engineer did not know of the change until 1978. The steel grade, the damper timing and the column placement are not identified as the source of the weakness. The bolted joints were the component that the engineer later described as underdesigned for the load.

Reasoning step 02 of 04

Why did the building's wind check miss the risk for more than a year?

Evidence-based explanation

The article reports that the New York building code required only the perpendicular wind case, and the braces had been checked only against it. The diagonal case, which loads the corners, was not part of the standard calculation. The damper explanation fails because the damper was never meant to be a safety device, and its electric power could fail in a storm. The 1978 strain figures contradict the idea that quartering winds were weaker for this building, although a 2019 analysis of a similar building reached the opposite result, which remains a live question. The height threshold is not in the record.

Reasoning step 03 of 04

Which reading of the storm-odds figures is best supported?

Evidence-based explanation

The figures are per-year estimates, built on weather records and on the damper's operation. The one-in-16 figure was calculated without the damper, and the one-in-55 figure assumed the damper kept running, which the article says might not hold in a major storm. The one-in-700 figure applied after the October repairs. Reading the numbers as best estimates, not guarantees, is the position the record supports.

Reasoning step 04 of 04

Which response to the storm threat is best supported by the record?

Evidence-based explanation

The New Yorker article describes an emergency-planning group that met on the morning of 1 September 1978, planned for a possible evacuation, and ended the plans on 13 September, after Hurricane Ella had turned out to sea. The repairs continued through the period, and the most critical joints had been fixed. Halting the work, ordering an immediate evacuation, or planning for no one are not what the record describes as the response.

04 · The findings

The chain behind the outcome.

In 1974 the wind-brace joints were changed from welds to bolts, and the New York office accepted the change without the engineer learning of it until 1978. The original calculations had checked the braces only against winds blowing straight at each face, which the code required. A student's question in June 1978 led the engineer to recalculate for diagonal winds, which raised the strain in some braces by about 40 percent. A check of the joints in late July then found that the bolted connections had been designed for perpendicular winds only, and the weakest was at the thirtieth floor. He estimated a one-in-16 annual chance of a storm that would break that joint without the damper, and one in 55 with the damper running. The repair welded steel plates over more than two hundred joints from August to October 1978, and the engineer later put the risk at one in 700 per year. Citicorp announced a review in August, but the work was largely unreported during a newspaper strike. When Hurricane Ella approached on 1 September, an emergency group planned for a possible evacuation; the storm turned out to sea, and the plans were ended on 13 September. Accounts differ on how the problem reached the engineer: the New Yorker describes an unnamed student from New Jersey who called his office, while the 2016 landmarks report names Diane Hartley, a Princeton graduate student, who raised it with the New York office.

Contributing causes and conditions

  1. The wind-brace joints were changed from welded to bolted in 1974, and the change was accepted without the engineer knowing of it.
  2. The original calculations checked the braces only against winds perpendicular to each face, as the code required.
  3. Quartering winds, which strike the corners diagonally, raised the strain in some braces by about 40 percent in the engineer's 1978 calculation, and the bolted joints were underdesigned for that load.
  4. The tuned mass damper reduced sway but depended on electric power, so it could not be counted on as a safety margin in a major storm.
  5. The repair welded steel plates over more than two hundred joints in 1978, and the public account was delayed until 1995.

OutcomeCiticorp Center wind-bracing crisis (1978)

Take the method with you

  1. A design check is only as broad as the load cases it includes, so ask which load directions the code and the calculation actually cover.
  2. A change made by one party, such as a joint type, can alter a structure without the designer knowing, so critical details need tracked approvals.
  3. Per-year risk figures help compare options, but they rest on assumptions, and a decision also needs a clear plan for who is told and when.

You can read findings at any time. Exploring every reasoning step marks this case as complete in your notebook.

Open another investigation

The open record

Sources & further reading

Read the original record and its scope before relying on a conclusion. Source references support the exhibit summaries; Faultory’s reasoning prompts are editorial reconstructions.

  1. s1
  2. s2
  3. s3
  4. s4

Written and curated for Faultory by Yunus Emre Vurgun, with AI-assisted research and drafting. Sources and interpretations can need correction. Read our editorial standards or report an issue.